H Street Reconstruction Project

Project Schedule and Phasing for H Street

The reconstruction for H Street continues to be on schedule and Phase 5 is near completion.

H Street improvements began on April 2, 2018 (Phases 1-4 are now complete).  

Street lights for H Street from 14th to 23rd Street have been energized.

H Street will be open from 14th Street to 27th Street, however, the intersection of 27th Street and H Street will be closed for the final phase of the project beginning Tuesday, October 2, 2018. 

The reconstruction project from 14th Street to 27th Street (1 mile) consists of replacing and rebuilding the roadway's pavement, curb and gutter system, installing sewer infrastructure, and constructing sidewalks throughout the corridor.

This nearly $2.5 million reconstruction project will be financed with existing revenue sources and is planned to be completed in the fall of 2018.

The links below provide additional details:




  1. Laura Bedlan

    Assistant Street Superintendent