H Street Reconstruction Project

Project Schedule and Phasing for H Street

Reconstruction for H Street has begun with underground utility work.  The Street will remain open during utility work, but may have limited access at times. 

Phase 1 improvements begin on April 2, 2018 and H. Street will be closed from 14th Street to 17th Street. Access between 14th Street and 17th Street will be limited to foot traffic only during the project phase. All other Phases will be open to traffic. 

In addition, mailboxes for Phase 1 will be temporarily moved/placed closer to the home (away from the construction area) by the contractor.

Alternative parking and access to each residence will be required.  Alternate parking ares for Phases 3,4  and 5 may include Jefferson Community Health & Life.

The reconstruction project will run from 14th Street to 27th Street (1 mile) and will consist of replacing and rebuilding the roadway's pavement, curb and gutter system, installing sewer infrastructure, and constructing sidewalks throughout the corridor.

This nearly $2.5 million reconstruction project will be financed with existing revenue sources and it is planned to be completed in the fall of 2018.

The links below provide additional details:




  1. Laura Bedlan

    Assistant Street Superintendent